This is the "." page of the "Library Director's Update: Panel Project" guide.
Alternate Page for Screenreader Users
Skip to Page Navigation
Skip to Page Content

Library Director's Update: Panel Project  

Last Updated: Jul 30, 2014 URL: http://libguides.oneonta.edu/panel Print Guide RSS UpdatesEmail Alerts
. Print Page
  Search: 
 

July 23 (Wednesday) Project Update

-- Ongoing panel installation: Enough panels on site to complete south elevation

-- Chilled water piping has progressed and is being connected in basement

-- All rough-ins of electrical completed; wire to be pulled next

-- Drop ceiling installation in progress

-- Floor patching progressing

-- Window frames have all been installed and glazing installation ongoing

-- Geography offices should be ready for move in on August 15
 

-- Stacks should be accessible to the public on or near the start of the academic year

      

    July 9 (Wednesday) Project Update

    -- Wednesday, July 9, is the last day to park in the parking lot behind Milne Library.  Frequent deliveries of materials will be commencing and storage space is required at this time.

    -- As soon as there is an adequate supply of panels onsite, Murnane (our contractor) will be putting (2) crews on the building and working 6 or 7 days per week project dependent.

    -- Over the course of the next two weeks, our contractor and subs will be putting up interior framing, installing some windows, roughing in electrical, finishing heat piping, installing air handlers and applying foam insulation.

        
       

      June 11 (Wednesday) Project Update

      Access points into the building will be sustained as much as possible until the courtyard area has been completed and main door access can resume. The contractor will attempt to keep to a 5-day workweek.  Weekends have been and may be added in the future depending upon weather and pace of project.  As of today, the project is moving forward according to plan.

      Today and rest of week:

      The structural engineer will be hammer / claw testing all clips attached to building.  These will ultimately be involved in hanging the panels.

      Glass has been delivered

      Interior doors and associated hardware to be delivered soon

       Next week:

      Metal-framing will ensue until completed

      Installation of clips to continue

       Two weeks ahead:

      Panels will be hung starting at the courtyard then progressing counter clockwise around the building

      Interior work will likely begin with the installation of new water and power lines from the sub-basement to the 3rd floor.  The contractor will notify us in advance when any disturbances are anticipated on any other floors.

       

      June 9 (Monday)

      The contractors will be working in the back area of the library removing panels today.  For today we need to use the lower ‘vehicle’ entrance to the back of the library so that we will not be under the cranes as they are working. It is anticipated that tomorrow the normal construction pathway in the back will be re-opened.  Thank you for your cooperation this summer.  It is greatly appreciated.

       

       

      June 3

      The Third Floor is no longer accessible via the elevator to ensure visitors' safety. Panel removal is now proceeding on the west side and around the atrium.

      The Jazzman's Cafe entrance is still the only public entrance.

      May 28

      - Access to Jazzmans entrance will need to be via walkway from Schumacher.  It is likely that the crane will take up the entire walkway between Chase and Milne.

      - The decision to close the upper parking lot behind Milne will be made by the contractor.   At present, limited parking is still available in the upper lot.

      - No delivery vehicles permitted w/in the fenced in lower lot adjacent to Milne's back door entrance.  Staff will need to use the designated walk way as marked, from the Schumacher / West Dorm Drive end of the parking area.  Please do not slip through the fence and cut across the other end of the lower lot near the heating plant.

          

        May 27

        - No vehicle or pedestrian entrance into the lower parking area (staff entrance) from the south (Heating Plant side).  Please enter at the north end (Schumacher side) and proceed along the eastern wall of the library to the doors.  Contractors will be placing scaffolding to mark walkways asap.

        - A crane will be arriving this week with closure of western sidewalks (Chase Gym side) in front of Milne to follow.

            

          May 21

          Entrance to Milne Library

          The doors to Jazzman’s and the rear service door entrance will be the access points until further notice. It will remain this way for a few weeks. The rear service door has an ADA compliant opener.

              

            May 14, 2014 Panel Project

            The General Contractor, Murnane Construction, will mobilize to our site on May 19. They will begin to establish the perimeter site fencing and restricted access areas, and begin internal dust barriers installation. Exterior caulk and window removal will begin over the main entrance courtyard as well. This activity will restrict access to the main entrance, and access through Jazzman’s will be required.

            We are planning on relocating the 3rd floor staff on Thursday, May 23. This includes the Geography, Women’s & Gender Studies, and ALS personnel. Room assignments in Ford and Fitzelle have been prearranged. Coordination with Telecom and IT will be a part of this migration.

            On May 27, the pre-cast panel removal will begin at the main entrance courtyard. This activity will continue on May 30 at the northwest corner and progress counterclockwise around the building over the ensuing 3 weeks. During that time, access points to the library will be adjusted to reflect the work progression. It is anticipated that use of the main entrance will be restored on or before June 6.

            As the summer progresses, a series of installations will be taking place following a similar pattern beginning at the northwest corner and progressing counterclockwise around the building. These processes include but are not limited to installation of structural framing, insulated panels, windows, electrical work, HVAC work, interior wall finishes, and flooring.

            The construction is scheduled to be substantially complete on August 1, with final completion following 2 weeks later on August 15. We expect that the staff migration back into the building will begin on Monday, August 11. As with all construction projects, all the dates anticipated in the description above are based on a prescriptive method that the contractor has provided. They are project milestones, and are subject to change based on unforeseen conditions.


                
              Description

              Loading  Loading...

              Tip